Annexation Process

 

The Gardnerville Water Company provides for the ability of property owners near or adjacent to the GWC boundaries to annex a parcel of land into the GWC service area boundary for water service.  The following are criteria, guidelines, fees, and approximate time frames to complete the annexation process.

 

 Click here for the GWC Annexation Process

 

Click here for the GWC Application for Annexation

 

 

Annexation Time-frame

The GWC engineer and staff prepare an "Engineer's Report" once the annexation is approved by the GWC Board of Directors.  Preparation of the Engineer's Report takes approximately two months to prepare (depending on the size of the development).  The Engineer's Report is then submitted to the Public Utilities Commission (PUC) for review and consideration by PUC staff and commission to determine if the development can be added to the GWC service area boundary.  The PUC review and approval usually takes approximately three months to complete.