Capital Improvements

                                     

 

The Gardnerville Water Company has developed a Capital Improvement Plan (CIP) for water system improvements.  This plan is updated each year by the GWC staff and is presented for approval to the GWC Board of Directors at the "Meeting of the Members" held on the second Tuesday of January each year.

The GWC reviews the 5 to 10 year CIP each year based on immediate and long range needs of the GWC water distribution system and also based on proposed street improvements for the Town of Gardnerville. 

Each year the Town of Gardnerville street improvement CIP is reviewed by the GWC staff and adjustments are made to the GWC CIP to ensure that water distribution improvements are made out ahead of the Town of Gardnerville street paving projects.  This insures that the streets will only be torn up one time.

 

Projected Capital Improvements

 

Year Description of Improvement
2019 Well #10
  Barton to Muller Loop
  Security Upgrades - Gate
  Surge Protection
  Office, Rental, and Well 3 Asphalt Seal
  Flexnet Communication
  Soft Start
  Exterior Paint
  Computer
Year Description of Improvement
2020 Exterior & Interior Tank Painting
  Scada Upgrades
  Parking Lot & Waterline Improvement
  Shop Driveway
  New Utility Truck (Duramax Replacement)
  Rehab of Well & Pump Replacement
  Fill Station Upgrades
Year Description of Improvement
2021 Backhoe Replacement
  Rehab of Well & Pump Replacement
  Storage Building
  Utility Software Upgrade
  Office, Rental, and Well 3 Asphalt Seal
  Computer
Year Description of Improvement
2022 VFD Replacement
  Towable Compressor
  Scada Computer and Programming
  Heaters
  Scada Upgrades
  Dump Truck Paint 
Year Description of Improvement
2023 Rehab of Well & Pump Replacement
  Server Computer and Programming
  Office, Rental, and Well 3 Asphalt Seal