Capital Improvements

                                     

 

The Gardnerville Water Company has developed a Capital Improvement Plan (CIP) for water system improvements.  This plan is updated each year by the GWC staff and is presented for approval to the GWC Board of Directors at the "Meeting of the Members" held on the second Tuesday of January each year.

The GWC reviews the 5 to 10 year CIP each year based on immediate and long range needs of the GWC water distribution system and also based on proposed street improvements for the Town of Gardnerville. 

Each year the Town of Gardnerville street improvement CIP is reviewed by the GWC staff and adjustments are made to the GWC CIP to ensure that water distribution improvements are made out ahead of the Town of Gardnerville street paving projects.  This insures that the streets will only be torn up one time.

 

Projected 10 Year Capital Improvements

 

Year Description of Improvement Location
2018 High School Street Waterline Extension  
  Shop Driveway Shop
  Storage Building Shop
  Barton to Muller Loop  
  BLM Tank Site High Pressure Survey  
  VFD & Motor (Well 3) Well #1, 2, 3
  Exterior Tank Painting 1.5 & 2.6 T
  Surge Protection All Wells, BP
  Well Meters Well #9
  Dump Truck Paint   
  Security Gate Electric Opener Shop
  Scada Upgrade Well #6
Year Description of Improvement Location
2019 Townhouse Circle to Mill Creek Loop  
  El Dorado to Village Waterline Improvement  
  Interior Tank Painting 1.5T
  New Utility Truck (Duramax Replacement)  
  Office, Rental, and Well 3 Asphalt Seal  
  Computer Manager, Accounting
  Exterior Paint 1394
  Video & Review of Casing Well #2
Year Description of Improvement Location
2020 Hwy 395 from Toler to Lampe Waterline Improvement  
  Interior Tank Painting 2.6T
  Park Place to Well 6 Intertie  
  Scada Upgrades  
  Parking Lot & Waterline Improvement 1394
  Jessica Lane Waterline Improvement  
  Rehab of Well & Pump Replacement Well #4
  Carpet & Interior Painting Office
  Utility Software Upgrade  
  Act Pack FS
Year Description of Improvement Location
2021 Waterloo from Smiths to Elges Waterline Improvement  
  Backhoe Replacement  
  Rehab of Well & Pump Replacement Well #1, #3
  Towable Compressor  
  Office, Rental, and Well 3 Asphalt Seal  
  VFD Replacement Well # 6
  Computer Reception, Operators
Year Description of Improvement Location
2022 Heaters All Wells, BP
  Scada Computer and Programming  
  Scada Upgrades  
Year Description of Improvement Location
2023 Rehab of Well & Pump Replacement Well #9
  Server Computer and Programming  
  Office, Rental, and Well 3 Asphalt Seal  
  VFD Replacement Well #4
  Automatic Transfer Switch Well #7
Year Description of Improvement Location
2024 Soft Starter Well #3
  Computer Manager, Accounting
  Act Pack Replacement Well #2
Year Description of Improvement Location
2025 Dump Truck Replacement  
  Rehab of Well & Pump Replacement Well #2, #6
  Generator, Automatic Transfer Switch, & VFD  Well #6, 9
  Office, Rental, and Well 3 Asphalt Seal  
  Act Pack FS
Year Description of Improvement Location
2026 Interior Tank Painting 1.5T
  Generator, Automatic Transfer Switch, & VFD  BP
  Exterior Tank Painting 1.5 & 2.6 T
  Computer Reception, Operators
  Exterior Paint 1394
Year Description of Improvement Location
2027 Rehab of Well & Pump Replacement Well #7
  Exterior Painting All Wells, Office
  Office, Rental, and Well 3 Asphalt Seal